Guide

Construction Site Supplies: Section 704, 110 V and Testing

Section 704 for site supplies: 110 V RLV Zs at 55 V, 30 mA and 500 mA RCDs, PME vs TT, ACS boards, IΔn RCD tests and three-monthly EICRs, with worked figures.

Published 22 September 2026 · Updated 14 November 2026 · Certio Software Ltd

Section 704 of BS 7671:2018+A4:2026 covers construction and demolition site installations, and its core rule is Regulation 704.410.3.10: every circuit feeding sockets or hand-held equipment up to 32 A needs reduced low voltage (RLV), a 30 mA RCD, electrical separation or SELV/PELV. Sockets above 32 A need an RCD of no more than 500 mA. The detail that catches people out is the 110 V loop impedance. At 55 V to earth, a B16 circuit's maximum Zs is about 0.65 Ω, roughly a quarter of the 230 V figure, so a 30 m extension lead can fail. This guide covers scope, earthing, Zs at 55 V, testing and certification.

Key takeaways
  • Section 704 covers the working site. Site offices, canteens, toilets and drying rooms follow the general rules of BS 7671.
  • Regulation 704.410.3.10: sockets and hand-held equipment up to 32 A need RLV, a 30 mA RCD, electrical separation or SELV/PELV. Note 1 prefers RLV for hand tools, hand lamps and local lighting up to 2 kW.
  • Sockets above 32 A need an RCD of no more than 500 mA, and Section 419 is not allowed for them.
  • Regulation 704.411.3.1: no PME unless every extraneous-conductive-part is reliably bonded. Expect a TT supply.
  • RLV circuits disconnect in 5 s (Regulation 411.8.3). Maximum Zs is worked at 55 V or 63.5 V, so a B16 at 55 V allows about 0.65 Ω, or 0.52 Ω at 80%.
  • Test RCDs at IΔn only, test both line conductors on 110 V circuits, and inspect at least every three months (IET Guidance Note 3).
  • Amendment 4 made no listed change to Section 704 or Regulation 411.8. SELECT's A4 summary names no change to either.

What does Section 704 cover, and what does it leave out?

Regulation 704.1 covers installations for new building work, repair, alteration, extension and demolition of existing buildings, engineering works, earthworks and similar work. It applies to the temporary installation from the supply intake, through the site distribution, to the final circuits. It keeps applying until the permanent installation takes over.

The administrative parts of the site are excluded. That means offices, cloakrooms, meeting rooms, canteens, restaurants, dormitories and toilets. A cabin with a small board, lights and 13 A sockets is designed like any other small commercial installation. The sub-main feeding that cabin from the site distribution is still Section 704 work.

Two documents sit alongside the regulations. BS 7375:2010 is the code of practice for distribution of electricity on construction and demolition sites. HSE's HSG141, Electrical safety on construction sites, came out in its second edition in April 2023. Main contractors build their site rules from both, so read them before you price a site job.

Which protective measures does Section 704 allow?

Circuit What Section 704 requires Regulation
Sockets up to 32 A and hand-held equipment up to 32 A RLV, or ADS with RCD ≤30 mA, or electrical separation (one item per source), or SELV/PELV 704.410.3.10
Sockets above 32 A RCD ≤500 mA; Section 419 not permitted 704.411.3.2.1
Means of earthing No PME unless all extraneous-conductive-parts reliably bonded to the MET 704.411.3.1
Obstacles, out of reach, non-conducting location, earth-free bonding Not permitted 704.410.3.5, 704.410.3.6
Distribution boards Assemblies for construction sites (ACS) to BS EN 61439-4 704.511.1
Plugs, sockets and couplers 16–125 A BS EN 60309-2 704.511.1
Supply isolation Device to isolate the site supply, securable in the OFF position 704.537.2

Sources: NICEIC technical summary of Section 704; Professional Electrician/NICEIC, "Requirements for the use of RLV systems on construction sites", 27 June 2023.

For the 500 mA RCD on sockets above 32 A, NICEIC gives the disconnection times as 5 s on TN systems and 1 s on TT systems. BS 7375 clause 7.1.2 recommends that the site isolator breaks all live conductors, including the neutral.

Why is 110 V the default for site tools?

The regulation does not mandate 110 V. The default comes from Note 1 to Regulation 704.410.3.10, HSG141 and contractors' site rules. A centre-tapped transformer limits the voltage to earth to 55 V on single-phase and 63.5 V on three-phase (Regulation 411.8.1.2), with 110 V between lines. A damaged drill lead on a wet slab is a very different event at 55 V than at 230 V.

The RLV rules sit in Regulation 411.8:

  • Source (411.8.4.1): a double-wound isolating transformer to BS EN 61558-2-23, a motor-generator with equivalent isolation, or an independent source such as a generator.
  • Earthing (411.8.4.2): the secondary is earthed at the midpoint (single-phase) or the star point (three-phase).
  • Fault protection (411.8.3): disconnection within 5 s at every point of utilisation, by an overcurrent device or RCD in each line conductor.
  • Accessories (411.8.5): plug earth contacts must not be interchangeable with any other system on the same site. BS EN 60309-2 handles this by colour and keyway: yellow for 100–130 V, blue for 200–250 V, red for 380–480 V.

Both conductors of a 110 V circuit are live to earth, so protective devices must break every line. That means double-pole on single-phase and triple-pole on three-phase. The IET's Wiring Matters (September 2020) warns that single-pole thermal-magnetic RCBOs designed for 230 V are generally unsuitable. Check that every device on the secondary side is rated for 110 V.

What is the maximum Zs on a 110 V circuit?

Table 41.6 gives the limits. NAPIT's technical guidance explains that they are the 230 V figures from Tables 41.3 and 41.4 scaled by 55/230 (0.239) or 63.5/230 (0.276). The same 0.95 Cmin factor applies, so you can check any figure yourself as Zs = 0.95 × U0 ÷ Ia.

Device Ia (5 s) Max Zs at 55 V (Ω) 80% at 55 V (Ω) Max Zs at 63.5 V (Ω) 80% at 63.5 V (Ω)
B16 80 A 0.65 0.52 0.75 0.60
B32 160 A 0.33 0.26 0.38 0.30
C16 160 A 0.33 0.26 0.38 0.30
C32 320 A 0.16 0.13 0.19 0.15

These are calculated values. Compare them with Table 41.6 in your own copy before you sign anything. The 80% column follows the usual Appendix 14 approach for comparing a cold test reading.

Worked example: how long can a 16 A yellow lead be?

Take a single-phase 110 V outlet on a B16 double-pole breaker, with a measured Zs of 0.20 Ω at the transformer outlet. Add an extension lead with 2.5 mm² cores. At 20 °C, 2.5 mm² copper is 7.41 mΩ/m, so the line-plus-cpc loop is 14.82 mΩ/m.

Lead length R1+R2 added (Ω) Zs at the end (Ω) Against 0.52 Ω (80% B16)
20 m of 2.5 mm² 0.30 0.50 Pass
30 m of 2.5 mm² 0.44 0.64 Fail
50 m of 2.5 mm² 0.74 0.94 Fail
20 m of 1.5 mm² (24.2 mΩ/m loop) 0.48 0.68 Fail

On these figures, about 21 m of 2.5 mm² is the limit at that outlet. A B32 at the same point leaves only about 0.06 Ω for the cable, which is around 4 m. That is why 32 A RLV circuits usually get a double-pole RCD, not an overcurrent device alone. Where an RCD gives fault protection, Zs × IΔn must not exceed 50 V, which allows up to 1,667 Ω at 30 mA.

Voltage drop gets worse on RLV in the same way. At 18 mV/A/m, 16 A on 50 m of 2.5 mm² loses about 14 V, which is 13% of 110 V. If that lead feeds a big SDS or a core drill, expect slow tools and nuisance complaints.

PME, TN-S or TT: what earthing will the site have?

Regulation 704.411.3.1 says PME should not provide the means of earthing unless every extraneous-conductive-part is reliably bonded to the main earthing terminal. On a site full of scaffold tube, rebar, temporary hoardings and steel containers, you cannot promise that. Network operators know it. UK Power Networks' guidance on temporary builders' connections says the supply will be TT, its earth terminal may not be used, and the customer must provide an RCD and an earth electrode. It gives the bonding requirements of the Electricity Safety, Quality and Continuity Regulations 2002 as the reason.

On a TT site, every circuit sits behind an RCD, and RA × IΔn must not exceed 50 V (Regulation 411.5.3). That allows 1,667 Ω at 30 mA, but only 100 Ω behind a 500 mA RCD. Size the rod and measure it properly: see Earth Electrode Testing for TT Systems: Methods and Limits. ENA ER G12/4 also says nothing exposed and conductive should be upstream of, or enclose, the origin RCD. NICEIC's guidance on BS 7375 clause 6.5.4.1 therefore prefers an all-insulated enclosure at the intake.

A generator is a third case. A set with a neutral-earth link and its own electrode is a local TN-S island. Get the hire company's earthing arrangement in writing and record it on the certificate. The three systems are compared side by side at Earthing Arrangements: TN-S, TN-C-S (PME, PNB) and TT.

How do you test a construction site installation?

The sequence is the normal one from IET Guidance Note 3 and Part 6. The site adds five complications.

  1. Both lines on 110 V. There is no neutral, so take R1+R2, Zs and PEFC for each line conductor and record the higher figure. NAPIT notes you get two PEFC values and one PSCC (line to line). Ipf can be calculated as 55 ÷ Zs.
  2. Zs stops at the secondary. On RLV, Zs is measured from the transformer secondary winding. The supply side is a separate circuit with its own reading.
  3. Instrument compatibility. Some three-wire loop testers expect neutral and earth at the same potential and will not work on a 55-0-55 V system. Use a two-wire test or an instrument rated for 110 V centre-tapped supplies.
  4. RCDs at IΔn only. Since Amendment 2, verification has been at the rated residual current, IΔn, with no 5 × IΔn test. Record the time and press the test button. On 110 V, confirm the RCD is rated for RLV. See RCD Testing Explained: The One Test BS 7671 Now Requires.
  5. Insulation resistance ages fast. A lead that read hundreds of megohms in spring can drop below 1 MΩ by summer once the sheath is nicked. Test transformers, ACS boards and site leads at every visit, not just the fixed sub-mains. See Low Insulation Resistance: Finding and Coding the Fault.

On three-phase distribution, check phase rotation at every 400 V outlet and balance the transformers across the lines. See Three-Phase Testing: Rotation, IR, Zs, PFC and RCDs.

What certificates and inspection intervals apply?

Section 704 has no special form. When the temporary installation is first energised, it gets an Electrical Installation Certificate with schedules of inspections and test results. Record the earthing arrangement, the electrode resistance, every ACS and the RLV transformer secondaries. Each extension is further work and needs its own EIC, or a Minor Works certificate where it is genuinely minor (see Electrical Installation Certificate (EIC) Explained, Section by Section).

IET Guidance Note 3 recommends no more than three months between periodic inspections of construction site installations, one of the shortest intervals it gives. Record each one as an EICR. Regulation 4(2) of the Electricity at Work Regulations 1989 requires systems to be maintained to prevent danger, so the duty is the dutyholder's, not just a recommendation. HSG141 adds user checks of tools and leads, plus regular visual checks of the distribution between formal inspections.

On the Amendment 4 model EICR, FI is an advisory classification, and only C1 and C2 make the report unsatisfactory. If you are still issuing on the earlier form, apply that form's own notes. For the code definitions, see EICR Observation Codes Explained: C1, C2, C3 and FI.

What observations come up most on site EICRs?

Finding Typical code Reasoning
Damaged flex with live cores exposed C1 Danger present
230 V sockets for hand tools on the working site with no 30 mA RCD C2 Breaches 704.410.3.10; potentially dangerous
110 V circuit Zs above the Table 41.6 limit, no RCD C2 No 5 s disconnection (411.8.3)
Single-pole device on an RLV circuit C2 One line left live on fault
Lead across a vehicle route with no ramp or catenary C2 Mechanical damage likely
Domestic consumer unit used as site distribution C2 or C3 Not an ACS to BS EN 61439-4; depends on location and condition
Site isolator cannot be locked off C3 704.537.2 not met
13 A plug fitted to a 110 V tool C2 Defeats 411.8.5 non-interchangeability
Earth electrode not tested, or result not recorded FI or limitation Cannot confirm RA × IΔn ≤ 50 V

The code is always your judgement on the day. Write the observation so the site manager can act on it before your van leaves. Phrasing guidance is at How to Write EICR Observations That Stand Up in 2026.

How Certio helps

Certio produces the EICR, EIC, Minor Works certificate and PAT records on the BS 7671 model forms and turns them into branded PDFs. Photograph the consumer unit and the circuit schedule drafts itself; point the phone camera at a Megger MFT-X1 and the reading goes straight into the schedule of test results, or dictate it while your hands stay on the probes. Suggested observation wording with the regulation reference is there for you to check and confirm. The judgement stays yours; the typing goes. Starter is £4.99 a month, charged when you sign up.

Straight answers

Questions

Is 110 V compulsory on a UK construction site?
Not by BS 7671 alone. Regulation 704.410.3.10 allows reduced low voltage, a 30 mA RCD, electrical separation or SELV/PELV for sockets and hand-held equipment up to 32 A. Note 1 to that regulation prefers RLV for portable hand lamps, hand tools and local lighting up to 2 kW, and most main contractors write 110 V into their site rules.
What is the maximum Zs on a 110 V B16 circuit?
On a single-phase 55-0-55 V system the formula gives 0.95 × 55 ÷ 80 A, about 0.65 Ω, for a 5 s disconnection. Apply 80% and a cold test reading should be no more than about 0.52 Ω. On three-phase RLV at 63.5 V to earth the figure is about 0.75 Ω. Check Table 41.6 in your copy of the regulations.
Can I use a PME earth on a temporary builders' supply?
Regulation 704.411.3.1 says PME should not be used unless all extraneous-conductive-parts are reliably bonded to the main earthing terminal, which is rarely achievable on a changing site. Many network operators simply supply temporary connections as TT. UK Power Networks, for example, says its builders' supplies are TT and its earth terminal must not be used.
How should I test RCDs on a site installation?
Test at the rated residual current, IΔn, and record the trip time. Since Amendment 2 BS 7671 no longer requires the 5 × IΔn test for verification, so drop it from site routines. On 110 V circuits confirm the RCD and its test button are rated for reduced low voltage, and test both line conductors because there is no neutral.
How often should a construction site installation be inspected?
IET Guidance Note 3 recommends a maximum of three months between periodic inspections of construction site installations. Issue an EIC when the temporary installation is first energised, a further certificate for each extension, and record each three-monthly visit as an EICR. HSG141 adds user checks and regular visual inspection between visits.
Less typing, same judgement

Down tools at 5. The paperwork's already done.

Certio lays out EICR, EIC, Minor Works and PAT certificates to the BS 7671 model forms and produces branded PDFs. Photograph the board and the schedule drafts itself; point the camera at a Megger MFT-X1 and the reading goes straight in. There's a free plan with no card. Starter is £4.99 a month and Pro £9.99 with unlimited certificates, charged when you sign up.

Get Starter · £4.99/mo →

More on EICR software and AI EICR software.