Guide

Continuity Testing: R1+R2 Method, Wander Lead and Values

Continuity testing explained: R1+R2 versus the wander lead method, nulling leads, expected mΩ/m values for twin and earth, the 1.2 factor and mistakes to avoid.

Published 14 September 2026 · Updated 14 September 2026 · Certio Software Ltd

Continuity testing proves that the protective conductor of every circuit runs unbroken from the main earthing terminal to each exposed-conductive-part, and it is the first dead test in the sequence set out in Chapter 64 of BS 7671:2018+A4:2026. There are two accepted methods. The R1+R2 method links line and cpc at the distribution board and measures the combined resistance at every outlet, giving a figure you reuse for Zs verification. The wander lead, or R2, method measures the cpc alone from the main earthing terminal. For a 2.5 mm² twin and earth circuit with a 1.5 mm² cpc, expect about 19.51 mΩ per metre at 20 °C, so a 25 m radial reads roughly 0.49 Ω.

Key takeaways
  • Null the leads before every session and after changing probes; unnulled leads add 0.1 to 0.3 Ω to every reading.
  • The R1+R2 method gives one figure that feeds straight into Zs = Ze + (R1+R2) × 1.2; the wander lead method only proves the cpc.
  • Compare readings against the mΩ/m figures for the cable size and length. Readings that are too low are as suspicious as readings that are too high.
  • Record the highest R1+R2 for each circuit, taken at the point furthest from the board.
  • Parallel paths through bonding, metal containment and other cpcs are the commonest cause of a false pass.

What is continuity testing and why is it done first?

Continuity testing is the measurement of the resistance of a conductor to confirm it is electrically unbroken and properly terminated. The cpc is the path fault current takes to operate the protective device, so a broken or high-resistance cpc means an earth fault may not clear in time. Chapter 64 of BS 7671 lists continuity of protective conductors, including main and supplementary bonding, as the first dead test, because a circuit with a broken cpc will pass insulation resistance perfectly and still be dangerous.

The instrument is the continuity range of a multifunction tester (MFT), which BS EN 61557-4 and Guidance Note 3 require to deliver a short-circuit test current of at least 200 mA; a multimeter on its buzzer range is not acceptable because its test current is too small to show up a poor crimp or a corroded terminal.

How does the R1+R2 method work?

The R1+R2 method measures the line conductor (R1) and the circuit protective conductor (R2) in series; the instrument sees the loop formed by the two.

Step by step

  1. Safely isolate the circuit and prove dead.
  2. Disconnect the circuit's line conductor from its protective device and link it to the cpc at the board with a short lead and two crocodile clips.
  3. Null the test leads (see below).
  4. At each outlet, switch, luminaire or accessory, measure between the line terminal and the earth terminal.
  5. The highest reading, normally at the point electrically furthest from the board, is the R1+R2 for the circuit.
  6. Remove the link and reinstate the line conductor before moving on.

For lighting circuits the switch must be on when you measure at the luminaire; for two-way and intermediate switching, test in each switch position so you have measured through the longest strap.

The value has a second use. Because the loop you measured is the loop fault current will take, Zs at the far end equals Ze plus R1+R2, corrected for temperature. A single set of readings verifies continuity and, after multiplying by 1.2, confirms Zs against the maximum Zs values in BS 7671 without a live loop test at every point.

How does the wander lead (R2) method work?

The wander lead method measures the protective conductor alone. One lead is connected to the main earthing terminal or the earth bar, and a long trailing lead, typically 20 to 50 m on a reel, is taken to each exposed-conductive-part in turn. Null the instrument with the full wander lead in circuit. The method suits points with no line conductor to link to: main bonding to gas and water, supplementary bonding in a bathroom, metal trunking and conduit, and extraneous-conductive-parts. Guidance Note 3 accepts both methods for proving continuity, but R2 alone cannot be used to calculate Zs.

R1+R2 method Wander lead (R2) method
What is measured Line and cpc in series cpc (or bonding conductor) alone
Link at the board Line to cpc, circuit isolated None; lead from MET
Gives Zs by calculation Yes, Zs = Ze + (R1+R2) × 1.2 No
Best for Final circuits on an EIC or EICR Bonding, containment, parts with no line conductor
Vulnerable to parallel paths Less so, but still possible via other cpcs Very, through pipework and structure

What should the readings be?

Expected values come from the resistance of copper per metre. The figures below are the standard IET On-Site Guide values for copper conductors at 20 °C, in milliohms per metre, and the combined R1+R2 for the common twin and earth pairings.

Conductor csa (mm²) Resistance (mΩ/m) at 20 °C
1.0 18.10
1.5 12.10
2.5 7.41
4.0 4.61
6.0 3.08
10.0 1.83
16.0 1.15
Twin and earth (line / cpc) R1+R2 (mΩ/m) at 20 °C 20 m run 30 m run
1.0 / 1.0 36.20 0.72 Ω 1.09 Ω
1.5 / 1.0 30.20 0.60 Ω 0.91 Ω
2.5 / 1.5 19.51 0.39 Ω 0.59 Ω
4.0 / 1.5 16.71 0.33 Ω 0.50 Ω
6.0 / 2.5 10.49 0.21 Ω 0.31 Ω
10.0 / 4.0 6.44 0.13 Ω 0.19 Ω
16.0 / 6.0 4.23 0.08 Ω 0.13 Ω

These are 20 °C values. Use the table as a sanity check rather than a pass mark: BS 7671 does not set a maximum R1+R2, it limits the resulting Zs. A reading two or three times higher than expected on a short run points to a loose terminal, a damaged conductor or a poor joint. A reading far too low, say 0.05 Ω on a 30 m lighting circuit that ought to read close to 1 Ω, almost certainly means you are reading through a parallel path rather than the cpc you think you are testing.

For ring final circuits the continuity test is a three-stage procedure using r1, rn and r2, covered in the guide on ring final circuit testing; the R1+R2 for a ring is (r1 + r2) ÷ 4.

Why multiply by 1.2 for Zs?

Under earth fault conditions the conductors are assumed to be at their maximum operating temperature, 70 °C for thermoplastic cable, where copper resistance is about 20 per cent higher than at 20 °C. So the design check is:

Zs (verified) = Ze + (R1+R2 measured) × 1.2

The result is compared with the maximum Zs for the device in Tables 41.2 to 41.4 of BS 7671. The alternative, when Zs is measured directly with a loop tester, is to compare against 0.8 times the tabulated maximum, as the On-Site Guide tables do. Do not apply both to the same figure. The earth fault loop impedance guide covers the live test.

How do you null the test leads?

Nulling, also called zeroing or lead compensation, removes the resistance of the leads from the reading. Short the probes firmly together, press null or zero, and confirm the display reads 0.00 Ω. Most MFTs hold the null until the range changes or the instrument is switched off, but some clear it whenever the dial moves, so check. Repeat the null whenever you change leads, add a wander lead or swap clips for probes. A pair of standard leads is typically 0.1 to 0.3 Ω, and a 50 m wander lead can be 0.5 Ω or more. If every reading on a modern board sits around 0.25 Ω regardless of circuit length, the leads were probably not nulled.

How are continuity results recorded?

On the schedule of test results enter the highest R1+R2 in ohms for each radial, and r1, rn, r2 and the derived R1+R2 for each ring. Where the wander lead method was used, enter the value in the R2 column and leave R1+R2 blank; the Appendix 6 model schedule has both columns so either method can be shown honestly.

Main and supplementary bonding continuity is recorded on the certificate itself. Guidance Note 3 suggests a main bonding conductor should read no more than about 0.05 Ω to the pipe it bonds; several ohms means a corroded clamp or a cable cut during other work. Do not record a test you did not do: an inaccessible accessory is a limitation, not a tick.

What are the common mistakes?

Mistake What happens How to avoid it
Not nulling the leads Every reading is 0.1 to 0.3 Ω high; short circuits look poor Null at the start and after any lead change
Parallel paths Reading far lower than the cable length allows; a broken cpc hides behind pipework or containment Estimate the expected value first; disconnect bonding for R2 tests where practicable; test with the cpc removed from the earth bar if in doubt
Testing with bonding connected on an R2 test Gas and water pipes return a low value and mask a missing cpc Isolate bonding for the test and record it as a limitation if it cannot be done
Switch off on a lighting circuit Open circuit at the luminaire Put switches on; check every position on two-way circuits
Measuring the nearest point only Recorded R1+R2 is not the maximum, so calculated Zs is optimistic Test at the furthest point; record the highest value
Leaving the link in place Line and cpc connected when the circuit is re-energised Make removing the link a fixed step before the next test

Parallel paths deserve the most attention. With metal back boxes, steel conduit and bonded pipework there are many routes back to the earth bar, and a cpc broken at a junction box can still read low through a back box screwed to a bonded pipe. Know roughly what the reading ought to be before you take it: if you expect 0.6 Ω and see 0.08 Ω, investigate rather than write it down.

How Certio helps

Certio produces the EICR, EIC, Minor Works certificate and PAT records on the BS 7671 model forms and turns them into branded PDFs. Photograph the consumer unit and the circuit schedule drafts itself; point the phone camera at a Megger MFT-X1 and the reading goes straight into the schedule of test results, or dictate it while your hands stay on the probes. Suggested observation wording with the regulation reference is there for you to check and confirm. The judgement stays yours; the typing goes. Starter is free for 7 days, then £5 a month.

Straight answers

Questions

What is the difference between the R1+R2 method and the wander lead method?
The R1+R2 method links line and cpc at the board and measures the loop resistance at each point on the circuit, giving one figure that is used later for Zs verification. The wander lead (R2) method measures the cpc alone from the main earthing terminal using a long trailing lead. Both prove continuity; only R1+R2 gives a value usable for Zs.
What should the R1+R2 reading be for a 2.5 mm² twin and earth circuit?
For 2.5 mm² line with 1.5 mm² cpc the combined figure is about 19.51 mΩ per metre at 20 °C, so a 20 m radial should read roughly 0.39 Ω and a 30 m run about 0.59 Ω. A reading far above that suggests a loose termination or a longer route than expected; a reading well below it points to a parallel path.
Why do I have to null the test leads before a continuity test?
Test leads and probes have their own resistance, typically 0.1 to 0.3 Ω, which is the same order as a short circuit's R1+R2. If you do not null or zero the leads, that resistance is added to every reading and a healthy 0.2 Ω circuit may appear as 0.5 Ω. Null with the probes shorted together and check the display reads 0.00 Ω.
Why is R1+R2 multiplied by 1.2 for Zs?
Continuity is measured with the conductors cold, at roughly 20 °C. Under fault conditions a 70 °C thermoplastic cable is assumed to be at its full operating temperature, where copper resistance is about 20 per cent higher. Multiplying the measured R1+R2 by 1.2 before adding Ze gives the worst-case Zs to compare against the maximum values in BS 7671.
Should main bonding be connected during a continuity test?
For the R1+R2 test the bonding can stay connected, because you are measuring line to cpc and gas or water pipes are not part of that loop. For the wander lead R2 method, bonding and any parallel earth paths can mask a broken cpc by returning a low reading through the pipework, so disconnect or isolate them where practicable and note it on the report.
Is a continuity test done dead or live?
Dead. Continuity of protective conductors and ring final circuit conductors is one of the dead tests in Chapter 64 of BS 7671, carried out after safe isolation and before insulation resistance. The tester uses a low d.c. test current of around 200 mA, and a live conductor would damage the instrument and give a meaningless reading.
Less typing, same judgement

Down tools at 5. The paperwork's already done.

Certio lays out EICR, EIC, Minor Works and PAT certificates to the BS 7671 model forms and produces branded PDFs. Photograph the board and the schedule drafts itself; point the camera at a Megger MFT-X1 and the reading goes straight in. Starter is free for 7 days, then £5 a month. Pro is £10 a month with unlimited certificates.

Try Starter free for 7 days →

More on EICR software and AI EICR software. Prices exclude VAT.